April 2015 sp3
HAYES TOWNSHIP
CONSTRUCTION PROGRESS UPDATE
APRIL 27, 2015
Attended by: Al Groudreau, Brian Rokosz, Joe Claybaugh
Jeff Finney, John Scherrer, Terry Acton , Maye Rood
Purpose of Update: Construction Progress Update
a. Gas Service with DTE
b. Tie-downs and Anchor bolts missing
c. Keyless entry system
d. Dishwasher in staff break room
e. Water softener connection for future
f. Electrical / septic pumps
g. Possible driveway changes (widen out at corner of north end)
h. Integrate security
i. Painting on Mezzanine
Subcontractor submittals needed ASAP for:
a. Stains for Glu-lams, & 2 x 6 T&G Roofing
b. Vinyl Fence /Dumpster enclosure
c. Glazing
d. Re-submittals on Metal Wall & Soffit Panels (layout drawings)
Submittals needed to be returned ASAP are:
a. Doors and frames, b. Brick, c. Cast Stone, d. Steel , e. Expansion joint,
f. Casework Bullet Resistant Equipment , g. Light fixtures , h. Flooring, I. Drywall,
j. Acoustical
Duct sizes – answered
Location of parking lot catch basin in reference to new wall - answered
Painting of Mezzanine – answered
Shaft wall – answered
LVL sized at main entry
Next Meeting Scheduled for: May 4th, 2015 @ 10:00 a.m.
With Special Board Meeting to follow @ 11:00 a.m.
Nancy Austin/ Hayes Township Clerk
04-27-2015